Build Progress
June 4, 2022
Date of GRAND OPENING!
Check out our Facebook page for speeches and additional images taken during the event.
4/14/2022
Completed:
Electrical is complete
Plumbing is complete
Pavers installed
Irrigation done
Interior is complete except just waiting on trim to arrive.
Exterior paint done
3/4/2022
Continued parking lot work
Septic system inspected and approved
Polished concrete floors - Completed
Installed flooring/base in gym
RR’s- Completed
Installed RR partitions
Worked on Low Voltage
2/18/2022
Parking lot work
Installed septic tank
Continued finish trim
Finished fireplace wall
Began polishing concrete floor
Prep floor in gym RR’s
2/4/2022
Inspected propane lines
Primed and painted walls
Installed lights in offices
HVAC is on.
Finish electrical
1/21/2022
Installed propane lines
Painting prep
Primed and painted walls
1/14/2022
Worked on final coat on gym floor
HVAC
Painting prep
Applied clear sealer to wood ceilings
1/7/2022
Worked on finishing gym floor
HVAC
Painting prep
12/17/2021
Paint HM Door/Frames
Refinishing Gym Floors
Drywall Taping
Installing HVAC
Installed Storefront Glass
11/19/2021
Installed Insulation
Installed Siding
Continued Parking Lot Work.
Continued Drywall
Cleaned out gym to prep for refinishing.
Permanent power turned on.
Lights are on.
11/5/2021
Installed Insulation
Roughed in Electrical and Plumbing.
Continued Parking Lot Work.
Started Drywall
HVAC
10/29/2021
Continued installing Septic.
Roughed in Electrical and Plumbing.
Continued Parking Lot Work.
Installed Interior Lights.
10/21/2021
Continued installing Septic.
Continued installing roof.
Roughed in Electrical and Plumbing.
Installed Overhead Doors.
Continued Parking Lot Work.
Removed Existing Siding Around Gym.
10/15/2021
Began installing Septic.
Continued installing roof.
Roughed in Electrical.
Installed Metal Doors and Hardware.
Began Parking Lot Work.
Removed Existing Siding Around Gym.
10/7/21
Continued installing stone.
Continued installing roof.
Roughed in Low Voltage.
Installed Storefront Doors in Gym
10/1/21
Continued installing stone.
Continued installing roof.
Installed HM frame
Installed water service.
Installing roof
9/24/2021
Continued electrical rough in.
Continued installing stone.
Installed HM frames.
Installed building wrap.
9/17/2021
Continued electrical rough in.
Began installing stone.
Installed HM frames.
Installed building wrap.
Grouted columns.
Stocked drywall.
8/27/2021
Continued electrical rough in.
Roof framing.
Sheeted roof.
Continued wood framing.
Patched sub floor in gym.
9/8/2021
Continued electrical rough in.
Patched gym flooring.
Installed windows.
Prepped HM door frames.
Install building wrap.
8/27/2021
Continued electrical rough in.
Patched gym flooring.
Installed windows.
Prepped HM door frames.
Install building wrap.
8/20/2021
Continued electrical rough in.
Roof framing
Installed trusses.
Continued wood framing.
Formed/poured pedestals.
Sheeted roof.
8/13/2021
Continued electrical rough in.
Installed ridge beams.
Installing trusses.
Continued wood framing.
Formed pedestals.
8/6/2021
Continued electrical rough in.
Poured more concrete.
Installed steel columns.
Continued wood framing
7/23/21
Installed rebar.
Excavated power trench.
Electrical rough in.
Painting continued in gym.
7/12/2021
Backfilled plumbing trenches.
Brought in 300 tons of rock.
Grading slab area.
Electrical rough in.
6/25/2021
Masonry is topped out.
Excavated for plumbing in existing building.
Filled in existing openings in gym.
6/18/2021
Formed footings.
Completed saw cuts.
CMU up to 20’.
Patched ceilings in gym.
Excavated for plumbing in gym RR area.
6/11/2021
Formed footings.
Filled in walls on existing building.
CMU up to 18’.
Grouted walls at 15’.
Plumbing lay out.
6/10/2021
Exterior walls begin to stack
Gym renovations continue
6/4/2021
Formed footings.
Installed rebar.
CMU up to 10’.
Plumbing lay out.
6/2/21
Some great updates/commitments – this is not a complete list but a great start! I am sure I miss some but working hard to keep track - Rich Duncan
SCE providing copies
CPI provided Temp power hook up
United Rental providing rental equipment
Statewide Fence providing fence rental
ACE Septic providing temp toilet
Owen Construction has the rough grade and build grading complete
Grant Co. Formed and poured footings
Salem Mobile mix provided concrete for footing
Ram Steel provide rebar and steel
Ashland Concrete Cutting providing concrete cutting
Carlson testing Providing on site testing
Murphy Plywood provided 5 units of plywood
Sign Crafters has donated some banners
The GK Machine was able to secure an emergency backup generator at a significant discount
The Detroit Foundation is going after a grant from USDA for the Generator
Pratum Co-op has found a Propane tank for the project
Freres Foundation has Donated the MMP beams and column
Withers has secured 90% of framing materials
- Looking for Trusses ?
Hardie – providing the siding
Fred Eichler Construction providing Framing
Davidson Masonry Has identified the stone for the exterior Wainscot
Davidson Masonry is providing materials and labor for the Apparatus bay building
Northside Electric with is suppliers has sourced all Electrical materials
- Looking for Electrician help for install
Salem Heating and Sheet metal secured the HVAC engineering
Working with Salem Heating, Santiam Heating, and Cascade Heating, we are sourcing HVAC package
IIS Mechanical along with Oregon Cascade and Do It Best and other suppliers we have the Plumbing covered
Mid Valley Commercial has the drywall and ceiling covered
Falls Insulation has the insulation covered
Summit Restoration has cleaned the Gym and is in the process of restoring fixtures
Thomas Kay Flooring is sourcing wood floor repair
LP Painting is painting the Gym
Rodda Paint is providing paint
Integrated solutions NW has committed to the low voltage
Hara’s windows has the vinyl windows
Blackline Glazing has the storefront Covered
Pfeifer Roofing along with Taylor metal has the metal roofing covered
Power Auto Group donated to sponsor the Overhead doors for the Apparatus bays
Salem Sign Co is working on the Score board for the Gym
Salem Sign Co is donating a Flag Pole
AC & Co has donated the Architecture work
Studio 3 Architecture has donated the Rendering work
WSC Engineers has donated the Structural Engineering
AKS Engineers has donated the Civil Engineering
Marion County waived the permit fees to the Foundation as a no profit doing a project for the community
Green Acres Landscape providing landscape drawings
Highway Fuel providing landscape materials
W H Cress Co providing toilet partitions
5/28/21
· Formed footings.
· Installed rebar.
· Special and County inspections.
· Poured footings.
· Sawcut interior floor and walls.
5/21/21
· Placed rock for subgrade and compacted.
· Continued cleaning in existing building.
· Layout for plumbing saw cuts.
5/14/2021
· Marked out building footprint.
· Got temp power turned on.
· Started excavation.
· Removed existing footings(underground)
· Continued demo/cleaning in existing building.
· Layout for plumbing saw cuts.
3/20/21
GROUNDBREAKING!